Street work to continue next week on 6th Street

men-working-1-2

 

Taking a look at next week’s paving schedule in the ongoing street rehabilitation project in Vincennes.

Starting Tuesday next week.. Milestone crews will begin full depth patching on 6th Street between Vigo and Busseron, 2nd Street between Minneapolis and Jefferson, Belle Crossing, 24th Street, Cullup St., and McKinnley Ave. between 20th Street and Forbes Rd. and Dailey Ave.

 

The work is expected to be completed by Friday.

 

Then starting the following Monday, September 14, Milestone crews will begin milling the remainder of the streets in the contract and begin applying the new surface. This work is expected to take 2 weeks.

There will be short term daytime closures for all the streets in the paving contract. These dates are subject to change due to weather conditions. Please use caution when in these areas.