Progress is being made on 2nd Street

men-working-1


It may not look like it, but work is progressing on the Second Street project in Vincennes.

City Engineer John Sprague says they are in the process of rebuilding the east side of the roadway. Sprague says most of the storm sewers have been installed with the exception of a couple of inlets near 2nd and Perry.

Sprauge told members of the city’s Redevelopment Commission that a crew will be in early next month to begin installing curbs. Paving should get underway by the middle of next month.

Initial completion of the project should be finished towards the end of October. Once completed….2nd Street between Hart and Main will have new sidewalks, paving, street lights and even a bicycle lane.